Buildings and Facilities17IH0060

CLUSTER 2017-003: REHABILITATION OF BUILDINGS, 1. REHABILITATION OF RHU, MONDRAGON RHU, 2. REHABILITATION OF RHU, ALLEN RHU, MONDRAGON & ALLEN, N. SAMAR

CLUSTER 2017-003: REHABILITATION OF BUILDINGS, 1. REHABILITATION OF RHU, MONDRAGON RHU, 2. REHABILITATION OF RHU, ALLEN RHU, MONDRAGON & ALLEN, N. SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱3,098,512.49. Status: Reported complete (DPWH). Contractor on record: MLU CONST. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control/drainage at Gastambide Street crossing SH Loyola, P. Noval and España Blvd.
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-16-0015236

₱1,076,412.00 · FY2016

Released to Melchor L. Nava National High School (Iloilo City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱3,098,512.49

Progress

Reported complete (DPWH)

Start Date

July 31, 2017

Target End

September 28, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.