Flood Control and Drainage19F00018

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF DAET RIVER CONTROL PROJECT, BRGY. LAG-ON, DAET, CAMARINES NORTE

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF DAET RIVER CONTROL PROJECT, BRGY. LAG-ON, DAET, CAMARINES NORTE is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱97,982,240.00. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱97,982,240.00

Progress

Reported complete (DPWH)

Start Date

October 30, 2019

Target End

January 5, 2021