Roads25IL0022

NETWORK DEVELOPMENT - ROAD WIDENING -SECONDARY ROADS - JCT. PANAN-AWAN AIRPORT RD - K1125+(-321) - K1125+480

NETWORK DEVELOPMENT - ROAD WIDENING -SECONDARY ROADS - JCT. PANAN-AWAN AIRPORT RD - K1125+(-321) - K1125+480 is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱28,851,282.50. Status: Past target date (DPWH On-Going). Contractor on record: J'NER CEPADA CONST. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tam-is Communal Irrigation System, Maasin City, Southern Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Southern Leyte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

41 projects · ₱219.6M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BATO-BONTOC RD - K1126+529 - K1126+740, K1128+828 - K1129+609

Southern Leyte 1st DEO, Region VIII

2024₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONCRETING OF BRGY. LAWGAWAN ROAD, BONTOC, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2022₱11.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES CONCRETING OF BRGY. HINAPU - BRGY. SAN AGUSTIN ROAD, MAASIN CITY, SO

Southern Leyte 1st DEO, Region VIII

2022₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CABUL-ANONAN, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱6.4M
Reported complete (DPWH)
No sat.

REHAB./MAJOR REPAIR OF PERMANENT CONCEPCION BRIDGE ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (B00317LT), CONCEPCION, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2016₱6.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, EVACUATION CENTER / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES, CONSTRUCTION OF EVACUATION CENTER, BARANGAY CABUL-ANONAN, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2022₱5.9M
Reported complete (DPWH)
View all 41 projects →

4. Implementation

Contract Amount

₱28,851,282.50

Progress

Past target date (DPWH On-Going)

Start Date

April 4, 2025

Target End

November 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.