Roads24PF0062

CONSTRUCTION OF LEPSIK-MABILIG FMR PHASE II, BRGY. KAYAPA, BAKUN, BENGUET

CONSTRUCTION OF LEPSIK-MABILIG FMR PHASE II, BRGY. KAYAPA, BAKUN, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,945,000.44. Status: Reported complete (DPWH). Contractor on record: SIKAAMO BUILDERS 53504. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Baguyos CIS Flood Control Structure along Baguyos Creek, Mankayan, Benguet
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Benguet 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,945,000.44

Progress

Reported complete (DPWH)

Start Date

July 22, 2024

Target End

December 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.