Flood Control and Drainage19CE0091

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DISTRICT I, CUYAPO, NUEVA ECIJA

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DISTRICT I, CUYAPO, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱1,880,258.62. Status: Reported complete (DPWH). Contractor on record: VERDAX BUILDERS. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,880,258.62

Progress

Reported complete (DPWH)

Start Date

June 11, 2019

Target End

August 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.