Flood Control and Drainage21DO0052

LOCAL PROGRAM- CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITES- CONSTRUCTION OF SLOPE PROTECTION AT BAUTISTA CREEK, BANLIK SUB URBAN VILLAG

LOCAL PROGRAM- CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITES- CONSTRUCTION OF SLOPE PROTECTION AT BAUTISTA CREEK, BANLIK SUB URBAN VILLAG is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱4,826,086.66. Status: Reported complete (DPWH). Contractor on record: ANROL CONST 10136. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱7,700,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Bulubok Creek, Brgy. Mangahan, Rodriguez, Rizal
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Rizal 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 10136

6 projects · ₱152.0M total · 0 flags

Other projects by this contractor

View all 6 projects →

4. Implementation

Contract Amount

₱4,826,086.66

Progress

Reported complete (DPWH)

Start Date

December 20, 2021

Target End

April 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.