Roads25IN0059

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - JCT HIMAY-ANGAN-SILAGO-ABUYOG BDRY RD K1073+454 - K1073+623

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - JCT HIMAY-ANGAN-SILAGO-ABUYOG BDRY RD K1073+454 - K1073+623 is a DPWH-tracked public work in Southern Leyte 2nd DEO, Region VIII. Reported contract value: ₱50,829,787.40. Status: Past target date (DPWH On-Going). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Southern Leyte 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tam-is Communal Irrigation System, Maasin City, Southern Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Southern Leyte 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 0 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱50,829,787.40

Progress

Past target date (DPWH On-Going)

Start Date

April 11, 2025

Target End

December 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.