Bridges22ED0102

CONSTRUCTION/IMPROVEMENT OF HANGING BRIDGE 2, BRGY. FORTUNA, SOCORRO, ORIENTAL MINDORO

CONSTRUCTION/IMPROVEMENT OF HANGING BRIDGE 2, BRGY. FORTUNA, SOCORRO, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱4,897,781.60. Status: Reported complete (DPWH). Contractor on record: MARC JILL CONST. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigating Structure along Mag-Asawang Tubig River, Sta. 0+000 - Sta. 0+360, San Andres Putik, Naujan, Oriental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Mindoro Oriental DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,897,781.60

Progress

Reported complete (DPWH)

Start Date

May 26, 2022

Target End

October 22, 2022

5. Audit