Bridges19KB0133

CONSTRUCTION OF HANGING STEEL BRIDGE, PUROK 11, BRGY DOLOGON, MARAMAG, BUKIDNON

CONSTRUCTION OF HANGING STEEL BRIDGE, PUROK 11, BRGY DOLOGON, MARAMAG, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱990,000.17. Status: Reported complete (DPWH). Contractor on record: XY BUILDERS. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱990,000.17

Progress

Reported complete (DPWH)

Start Date

October 16, 2019

Target End

December 14, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.