Roads25J00110

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ CAMAN-GA - TABUAN - MANLAYAG - NAVALAN BY-PASS ROAD, ZAMBOAN-GA DEL SUR

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ CAMAN-GA - TABUAN - MANLAYAG - NAVALAN BY-PASS ROAD, ZAMBOAN-GA DEL SUR is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱44,996,508.54. Status: Past target date (DPWH On-Going). Contractor on record: ZMS CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱44,996,508.54

Progress

Past target date (DPWH On-Going)

Start Date

March 14, 2025

Target End

November 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.