Buildings and Facilities19EH0111

COMPLETION OF MULTI - PURPOSE BUILDING (COVERED COURT), CAMBIJANG, CAJIDIOCAN, ROMBLON

COMPLETION OF MULTI - PURPOSE BUILDING (COVERED COURT), CAMBIJANG, CAJIDIOCAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱2,449,841.91. Status: Reported complete (DPWH). Contractor on record: MT GUITING-GUITING CONST 17412. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,449,841.91

Progress

Reported complete (DPWH)

Start Date

July 8, 2019

Target End

October 15, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.