Water Provision and Storage17L00208

CONSTRUCTION/REHABILITATION OF WATER SUPPLY (LEVEL II) IN REGION XI, VARIOUS LOCATION IN REGION XI

CONSTRUCTION/REHABILITATION OF WATER SUPPLY (LEVEL II) IN REGION XI, VARIOUS LOCATION IN REGION XI is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱28,037,486.88. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,037,486.88

Progress

Reported complete (DPWH)

Start Date

February 25, 2018

Target End

October 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.