Flood Control and Drainage20I00075

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, STA. ELENA SECTION, TANAUAN, LEYTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, STA. ELENA SECTION, TANAUAN, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱95,424,703.75. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱95,424,703.75

Progress

Reported complete (DPWH)

Start Date

December 3, 2020

Target End

November 27, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.