GAA 2025 SSP25NH0075

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY BITAUGAN EAST, CAGWAIT, SURIGAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY BITAUGAN EAST, CAGWAIT, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 1st DEO, Region XIII. Reported contract value: ₱9,677,831.98. Status: Past target date (DPWH On-Going). Contractor on record: ROWIE'S CONST. Figures trace to dpwh.

Surigao del Sur 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Bayan, Marihatag, Surigao del Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Surigao del Sur 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,677,831.98

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

December 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.