Roads23N00137

CABADBARAN-PUTING BATO-LANUZA ROAD, PACKAGE 8, LANUZA, SURIGAO DEL SUR

CABADBARAN-PUTING BATO-LANUZA ROAD, PACKAGE 8, LANUZA, SURIGAO DEL SUR is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱72,374,985.62. Status: Reported complete (DPWH). Contractor on record: J M LUCIANO CONST INC. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱72,374,985.62

Progress

Reported complete (DPWH)

Start Date

March 27, 2023

Target End

March 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.