Flood Control and Drainage20IB0011

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG DOLORES RIVER POBLACION 1 AND 2, MASLOG, EASTERN SAMAR

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG DOLORES RIVER POBLACION 1 AND 2, MASLOG, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱19,599,996.14. Status: Reported complete (DPWH). Contractor on record: DAYBREAK ENT - ENGINEERING. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,599,996.14

Progress

Reported complete (DPWH)

Start Date

February 18, 2020

Target End

October 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.