GAA 2025 OO-125A00187

ROAD WIDENING - PRIMARY ROADS - MANILA NORTH RD - K0489 + 957 - K0489 + 979, K0489 + 996 - K0490 + 000, K0554 + 500 - K0555 + 069, K0555 + 347 - K0555 + 402, K0555 + 498 - K0555 + 534, K0555 + 586 - K0555 + 896, K0555 + 1074 - K0557 + 713, K0558 + 032 -

ROAD WIDENING - PRIMARY ROADS - MANILA NORTH RD - K0489 + 957 - K0489 + 979, K0489 + 996 - K0490 + 000, K0554 + 500 - K0555 + 069, K0555 + 347 - K0555 + 402, K0555 + 498 - K0555 + 534, K0555 + 586 - K0555 + 896, K0555 + 1074 - K0557 + 713, K0558 + 032 - is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱119,743,321.72. Status: Past target date (DPWH On-Going). Contractor on record: KATHA BUILDERS. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

236 projects · ₱11.1B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL J

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱246.1M
Reported complete (DPWH)
No sat.

BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, GUISSET - BINGA - BALOY - TINONGDAN (SECTION 5 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETITOGON, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱231.6M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF PIMINGGAN - SAGUITLANG - LUBAS - DUNGON ROAD IN SUPPORT TO COFFEE, CACAO, BAMBOO, GOLD, LIVESTOCK,

Cordillera Administrative Region, Cordillera Administrative Region

2022₱198.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION / UPGRADING OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS CITY LIMIT - STO TOMAS ROADKO255+1085

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
View all 236 projects →

4. Implementation

Contract Amount

₱119,743,321.72

Progress

Past target date (DPWH On-Going)

Start Date

February 24, 2025

Target End

December 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.