Roads16GI0044

REHABILITATION/RECONSTRUCTION/UPGRADING OFDAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE, NEW LUCENA - STA BARBARA ROAD, K0016+(-467) - K0016+423.45 WITH EXCEPTION, K0018+894 - K0019+517

REHABILITATION/RECONSTRUCTION/UPGRADING OFDAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE, NEW LUCENA - STA BARBARA ROAD, K0016+(-467) - K0016+423.45 WITH EXCEPTION, K0018+894 - K0019+517 is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱25,824,488.54. Status: Reported complete (DPWH). Contractor on record: EAST ASIA CONST INC. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Tigum Flood Control Project (Jaro - Tigum River), Brgy. Purok I, Poblacion, Pavia, Iloilo 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0028783

₱9,561,000.00 · FY2016

Released to Naval State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱25,824,488.54

Progress

Reported complete (DPWH)

Start Date

August 4, 2016

Target End

March 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.