Roads17CC0014

REPAIR/REHABILITATION OF BARANGAY ROADS BRGY. MALAMIG, BUSTOS, BULACAN

REPAIR/REHABILITATION OF BARANGAY ROADS BRGY. MALAMIG, BUSTOS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱2,925,740.70. Status: Reported complete (DPWH). Contractor on record: WBX CONST INC FORMERLY WBX CONST 28370. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,925,740.70

Progress

Reported complete (DPWH)

Start Date

March 3, 2017

Target End

April 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.