Buildings and Facilities16GI0047

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY DUSACAN, LEON, ILOILO

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY DUSACAN, LEON, ILOILO is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱1,959,626.92. Status: Reported complete (DPWH). Contractor on record: PATRILA BUILDERS INC 26628. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,959,626.92

Progress

Reported complete (DPWH)

Start Date

September 1, 2016

Target End

December 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.