Roads25CN0166

CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORA

CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱23,895,431.30. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: R N G M CONST CORP FORMERLY: R N G M CONST 20281. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱23,895,431.30

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.