Buildings and Facilities18KB0121

CONSTRUCTION OF 1 UNIT, 1 STY - 3 CL WITH TOILET ATTACHED AT KIMOLONG ES, KIMOLONG, KITAOTAO, BUKIDN

CONSTRUCTION OF 1 UNIT, 1 STY - 3 CL WITH TOILET ATTACHED AT KIMOLONG ES, KIMOLONG, KITAOTAO, BUKIDN is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱4,412,335.29. Status: Reported complete (DPWH). Contractor on record: XY BUILDERS. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,412,335.29

Progress

Reported complete (DPWH)

Start Date

September 6, 2018

Target End

December 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.