Bridges15B00092

CONST'N & MAINTENANCE OF BRIDGES ALONG NAT'L RDS: RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES: L

CONST'N & MAINTENANCE OF BRIDGES ALONG NAT'L RDS: RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES: L is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱3,894,595.88. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Region II, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱3,894,595.88

Progress

Reported complete (DPWH)

Start Date

March 14, 2016

Target End

May 15, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.