Bridges24FB0222

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION (COMPLETION) OF PAWA-BOGTONG BRIDGE ALONG SAN JOAQUIN-PAWABOGTONG ROAD

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION (COMPLETION) OF PAWA-BOGTONG BRIDGE ALONG SAN JOAQUIN-PAWABOGTONG ROAD is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱115,783,456.63. Status: Past target date (DPWH On-Going). Contractor on record: HI-TONE CONST & DEVELOPMENT CORP FORMERLY 23385. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Barangay Namantao, Daraga, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 23385

124 projects · ₱13.3B total · 0 flags

Other projects by this contractor

No sat.

DESIGN AND BUILD OF COASTAL DIKE AND DRAINAGE IMPROVEMENT, CATBALOGAN CITY, SAMAR

Flood Control Management Cluster, Central Office

2019₱744.4M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTION OF BICOL REGIONAL HOSPITAL AND MEDICAL CENTER (MEDICAL ARTS BUILDING AND FACILITIES, PATIENT'S ROOM AND TRAINING CENTER), DARAGA, ALBAY, DARAGA,

Region V, Region V

2023₱475.3M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTON 0F BICOL UNIVERSITY CONVENTION AND DISASTER RISK REDUCTION MANAGEMENT CENTER, DARAGA, ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱374.4M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BATO LAKESHORE DIKE ROAD(CIRCUMFERENTIAL ROAD) IN SUPPORT OF AGRIC

Region V, Region V

2023₱279.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF COASTAL ROAD AND SHORE P

Region V, Region V

2024₱279.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF NBI BUILDING, REGIONAL OFFICE V, REGIONAL GOVERNMENT CENTER, RAWIS, LEGAZPI, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2023₱241.5M
Past target date (DPWH On-Going)
View all 124 projects →

4. Implementation

Contract Amount

₱115,783,456.63

Progress

Past target date (DPWH On-Going)

Start Date

October 8, 2024

Target End

July 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.