CONCRETING OF LAM APOS FMR (INCLINED PORTION), BRGY. LAM-APOS, BANGA, SOUTH COTABATO

CONCRETING OF LAM APOS FMR (INCLINED PORTION), BRGY. LAM-APOS, BANGA, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱4,904,468.49. Status: Reported complete (DPWH). Contractor on record: THREE G BUILDERS 43055. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,904,468.49

Progress

Reported complete (DPWH)

Start Date

September 5, 2018

Target End

December 13, 2018