GAA 2025 SSP25AF0130

BASIC INFRA PROGRAM (BIP), REHABILITATION OF MULTI-PURPOSE BLDG (COVERED COURT), BARANGAY SAMARA, ARINGAY, LA UNION

BASIC INFRA PROGRAM (BIP), REHABILITATION OF MULTI-PURPOSE BLDG (COVERED COURT), BARANGAY SAMARA, ARINGAY, LA UNION is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱4,750,621.68. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: AYANA CONST AND TRADING. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bauang River Basin, Package 2, Barangay Cabalayangan, Bauang, La Union
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

La Union 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,750,621.68

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 14, 2025

Target End

September 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.