Roads17KI0006

CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL RD., OROQ.-PLA-CAL.-S DALAGA ROAD, K1745+256-K1745+360; K1746+000-K1746+180;K1747+610-K1748+000; K1758+393-K1758+258;K1758+780-K1759+020;K1759+570-K1759+750;K1760+120-1760+260;K1760+633-K1761+114;K1761+17

CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL RD., OROQ.-PLA-CAL.-S DALAGA ROAD, K1745+256-K1745+360; K1746+000-K1746+180;K1747+610-K1748+000; K1758+393-K1758+258;K1758+780-K1759+020;K1759+570-K1759+750;K1760+120-1760+260;K1760+633-K1761+114;K1761+17 is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱21,666,797.24. Status: Reported complete (DPWH). Contractor on record: VICTORIANO C LIM CONST CORP FORMERLY: VICTORIANO C LIM CONST. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mambayaan Flood Control Structure (Ground Sill) Project, Brgy. Mambayaan, Balingasag along Balatukan River, Misamis Oriental
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0023133

₱15,461.00 · FY2017

Released to Division of Compostela Valley (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱21,666,797.24

Progress

Reported complete (DPWH)

Start Date

May 18, 2017

Target End

November 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.