Roads20IL0203

CONCRETING OF BRGY. NAHULID FMR, BRGY. NAHULID, LIBAGON, SOUTHERN LEYTE

CONCRETING OF BRGY. NAHULID FMR, BRGY. NAHULID, LIBAGON, SOUTHERN LEYTE is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱12,500,000.00. Status: Reported complete (DPWH). Contractor on record: JQD CONST. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

250 projects · ₱2.7B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SOGOD TO BUENAVISTA, BONTOC BYPASS ROAD, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BYPASS AND DIVERSION ROADS - MAASIN CITY COASTAL BYPASS ROAD (WEST BYPASS ROAD SEGMENT 8), SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF PANCIL - AURORA - CADARU

Southern Leyte 1st DEO, Region VIII

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MAASIN CITY COASTAL BYPASS ROAD (WEST BYPASS ROAD SEGMENT 7), SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMS, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAASIN AIRPORT, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2022₱96.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SOGOD TO BUENAVISTA, BONTOC BYPASS ROAD, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2025₱76.3M
Past target date (DPWH On-Going)
View all 250 projects →

4. Implementation

Contract Amount

₱12,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 2, 2021

Target End

August 28, 2021

5. Audit