Buildings and Facilities23BD0048

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY GADU, SOLANA, CAGAYAN

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY GADU, SOLANA, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱2,475,000.00. Status: Reported complete (DPWH). Contractor on record: JVC CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Pinacanauan River, Barangay Quibal, Pe±ablanca, Cagayan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cagayan 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

18 projects · ₱98.0M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY CARIG SUR, TUGUEGARAO CITY, CAGAYAN VALLEY

Cagayan 3rd DEO, Region II

2024₱17.8M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF PROVINCIAL ENVIRONMENTAL AND NATURAL RESOURCES OFFICE (PENRO), TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱11.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PARUG - PARUG, SOLANA, CAGAYAN - PACKAGE 2

Cagayan 3rd DEO, Region II

2024₱9.9M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF BUILDING, ANNAFUNAN INTEGRATED SCHOOL, BRGY. ANNAFUNAN EAST, TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2023₱7.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF PROVINCIAL ENVIRONMENT AND NATURAL RESOURCES OFFICE (PENRO), TUGUEGARAO CITY, CAGAYAN - PHASE II

Cagayan 3rd DEO, Region II

2025₱6.8M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BABAYUAN, AMULUNG, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱5.0M
Reported complete (DPWH)
View all 18 projects →

4. Implementation

Contract Amount

₱2,475,000.00

Progress

Reported complete (DPWH)

Start Date

April 21, 2023

Target End

August 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.