Buildings and Facilities18IE0083

CONSTRUCTION OF A MULTI-PURPOSE BUILDING, SAN ISIDRO CENTRAL SCHOOL, SAN ISIDRO, LEYTE

CONSTRUCTION OF A MULTI-PURPOSE BUILDING, SAN ISIDRO CENTRAL SCHOOL, SAN ISIDRO, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱2,405,459.65. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

692 projects · ₱17.7B total · 0 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱2,405,459.65

Progress

Reported complete (DPWH)

Start Date

June 11, 2018

Target End

October 8, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.