Buildings and Facilities17ID0166

CONSTRUCTION OF 1 UNIT,1 STOREY,3 CLASSROOM SCHOOL BUILDING WITH THREE(3)UNITS-TOILET ATTACHED AT BAGACAY EAST PS,BRGY. BAGACAY EAST,LA PAZ,LEYTE

CONSTRUCTION OF 1 UNIT,1 STOREY,3 CLASSROOM SCHOOL BUILDING WITH THREE(3)UNITS-TOILET ATTACHED AT BAGACAY EAST PS,BRGY. BAGACAY EAST,LA PAZ,LEYTE is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱4,049,148.56. Status: Reported complete (DPWH). Contractor on record: WJ BUILDERS. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱17,995,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Sitio Bariis River Brgy. East Visoria, Carigara, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Leyte 2nd DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,049,148.56

Progress

Reported complete (DPWH)

Start Date

January 17, 2018

Target End

May 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.