Flood Control and Drainage17BF0024

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJECT VILLA FUGU-PANICIEN SECTION, STA.0+000-STA.0+500, AURORA, ISABELA, VILLA FUGU AND PANICIEN, AURORA, ISABELA

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJECT VILLA FUGU-PANICIEN SECTION, STA.0+000-STA.0+500, AURORA, ISABELA, VILLA FUGU AND PANICIEN, AURORA, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱18,616,208.01. Status: Reported complete (DPWH). Contractor on record: MAR-DEB CONST. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

229 projects · ₱6.7B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAUAYAN CITY BYPASS ROAD, ISABELA

Region II, Region II

2024₱149.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R. A. 11239 - PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY - K0349+012 - K0350+700 , K0358+005 - K0358+581

Region II, Region II

2025₱130.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAUAYAN CITY BYPASS ROAD - PACKAGE 1, ISABELA

Region II, Region II

2023₱115.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF PANANG FLOOD CONTROL STRUCTURE, SECTION 2, SAN AGUSTI

Isabela 4th DEO, Region II

2025₱106.1M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF CAGAYAN RIVER FLOOD CONTROL PROJECT, BRGY. DISTRICT I, REINA

Isabela 3rd DEO, Region II

2024₱99.0M
Reported complete (100% progress, DPWH status On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJECT, BRGY. BANQUERO, REINA MERCEDES, ISABELA

Isabela 3rd DEO, Region II

2024₱99.0M
Reported complete (DPWH)
View all 229 projects →

4. Implementation

Contract Amount

₱18,616,208.01

Progress

Reported complete (DPWH)

Start Date

February 19, 2017

Target End

January 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.