Construction of Flood Mitigation Structure22EH0061

Construction of Ilaya-Ayog-og Flood Control Structure Phase II, San Agustin, Romblon

Construction of Ilaya-Ayog-og Flood Control Structure Phase II, San Agustin, Romblon is a DPWH-tracked public work in SAN AGUSTIN (ROMBLON), ROMBLON, Region IV-B. Reported contract value: ₱24,499,249.85. Status: Reported complete (DPWH). Contractor on record: EMQ DESIGN & CONST. Figures trace to sumbong.

SAN AGUSTIN (ROMBLON), ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003003

₱545,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002921

₱50,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱24,499,249.85

Progress

Reported complete (DPWH)

Start Date

April 12, 2022

Target End

October 31, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.