Flood Control and Drainage24FB0073

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF RIVERBANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BRGY.PANDAN-BRGY.BONGALONRIVER

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF RIVERBANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BRGY.PANDAN-BRGY.BONGALONRIVER is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱47,527,540.92. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ELKANKONSTRAK DEVELOPMENT CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Dike ) with Drainage System along Taysan, Legazpi City, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

57 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2024₱141.3M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2023₱140.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD - SECONDARY ROADS - ALBAY WEST COAST ROAD (MARIGONDON SECTION), KO551 + 680.00 - KO552 + 1

Albay 3rd DEO, Region V

2024₱140.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-GUINOBATAN-JOVELLAR-DONSOL ROAD LEADING TO PILAR PORT, GUINOBATAN AND JOVELLAR, ALBAY, GU

Region V, Region V

2023₱102.4M
Past target date (DPWH On-Going)

Construction of Revetment along Downstream of Hamorawon Bridge, Pili, Camarines Sur

PILI (CAPITAL) (CAMARINES SUR), CAMARINES SUR, Region V

2023₱95.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱93.6M
Past target date (DPWH On-Going)
View all 57 projects →

4. Implementation

Contract Amount

₱47,527,540.92

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 17, 2024

Target End

November 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.