Buildings and Facilities16FN0049

CLUSTER: CONSTRUCTION OF TWO (2) STOREY, SIX (6), TEN (10) AND FOUR (4) CLASSROOM SCHOOL BUILDING AT RAGAY, CAMARINES SUR

CLUSTER: CONSTRUCTION OF TWO (2) STOREY, SIX (6), TEN (10) AND FOUR (4) CLASSROOM SCHOOL BUILDING AT RAGAY, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 1st DEO, Region V. Reported contract value: ₱36,475,900.00. Status: Reported complete (DPWH). Contractor on record: NFH CONST. Figures trace to dpwh.

Camarines Sur 1st DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation and Improvement of Camaligan Flood Control (Bicol River), Brgy. Mangayawan, Canaman, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0009922

₱8,295,800.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

123 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS-MABOLO-ALMEDA BYPASS ROAD, NAGA CITY, CAMARINES SUR 3RD LEGISLATIVE DISTRICT

Region V, Region V

2021₱226.8M
Reported complete (DPWH)
No sat.

CONST./IMPV'T. OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS - JCT. MORNING, CATAINGAN-ESPERANZA PORT ROAD, PIO V. CORPUZ AND ESPERANZA, MASBATE 3RD LD

Region V, Region V

2016₱202.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 7, CAMARINES SUR, PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS -NASUGBU-LIAN-CALATAGAN RD (S05012LZ) - K0113 + 600 - K0114 + 000, K0115 + 000 - K0116 + 400

Batangas 1st DEO, Region IV-A

2024₱144.8M
Reported complete (DPWH)
No sat.

CONST./IMPV'T. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ROAD UPGRADING (GRAVEL TO CONCRETE) OF SAN JUAN-ALAS-TAGPU-DAYAO ROAD LEADING TO MANDAON ECOTOURISM SITES, MANDAON, MASBATE PROVINCE

Region V, Region V

2016₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO283+040 - KO292+200 WITH EXCEPTIONS, CAMARINES NORTE

Region V, Region V

2016₱142.9M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱36,475,900.00

Progress

Reported complete (DPWH)

Start Date

August 25, 2016

Target End

March 17, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.