Flood Control and Drainage20CE0039

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER, BRGY. PARANG MANGGA, SAN JOSE CITY, NUEVA ECIJA

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER, BRGY. PARANG MANGGA, SAN JOSE CITY, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱32,927,989.58. Status: Reported complete (DPWH). Contractor on record: WIZARD CONCRETE SOLUTIONS AND CONST CORP FORMERLY: WIZARD TRADING. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

210 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, MERCED

Region V, Region V

2024₱144.6M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS, BALER-DAANG MAHARLIKA (LZ), PROVINCE OF NUEVA ECIJA

Region III, Region III

2021₱101.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADS, PANTABANGAN-CANILI-BASAL-BALER ROAD, PROVINCE OF NUEVA ECIJA

Region III, Region III

2021₱98.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF P-5 BORABOD TO AWITAN ROAD, DA

Region V, Region V

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PALESTINA, SAN JOSE CITY, NUEVA ECIJA

Nueva Ecija 1st DEO, Region III

2019₱96.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0166+005 - K0166+662, K0135+551.60 - K0135+628, K0137+000 - K0137+386, K0143+304 - K0143+438, K0149+000 - K0149+427, K0149+442 - K0150+446, K0155+080

Nueva Ecija 1st DEO, Region III

2019₱96.1M
Reported complete (DPWH)
View all 210 projects →

4. Implementation

Contract Amount

₱32,927,989.58

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

October 22, 2020

5. Audit