Construction of Flood Mitigation Structure23CE0031

Construction of Flood Control Structure along Labong River, Barangay Villarosa, (Phase 6), Licab, Nueva Ecija

Construction of Flood Control Structure along Labong River, Barangay Villarosa, (Phase 6), Licab, Nueva Ecija is a DPWH-tracked public work in LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱96,495,000.00. Status: Reported complete (DPWH). Contractor on record: AMP 723 CONST CORP FORMERLY: A M P CONST / IJK MAE CONST INC. Figures trace to sumbong.

LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Labong River, Barangay Poblacion Sur, Licab, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0024916

₱371,572.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,495,000.00

Progress

Reported complete (DPWH)

Start Date

February 22, 2023

Target End

November 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.