Buildings and Facilities19FN0183

CONSTRUCTION OF THREE (3) STOREY, TWO (2) REGULAR WORKSHOP, TWO (2) SCIENCE LABORATORY, TWO (2) ICT LABORATORY BUILDING (PHASE I), BARCELONITA, CABUSAO, CAMARINES SUR

CONSTRUCTION OF THREE (3) STOREY, TWO (2) REGULAR WORKSHOP, TWO (2) SCIENCE LABORATORY, TWO (2) ICT LABORATORY BUILDING (PHASE I), BARCELONITA, CABUSAO, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 1st DEO, Region V. Reported contract value: ₱51,340,000.00. Status: Reported complete (DPWH). Contractor on record: R D MANDANAS CONST. Figures trace to dpwh.

Camarines Sur 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-19-0018815

₱0.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

107 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (KALINGA PROVINCIAL HOSPITAL OR-DR COMPLEX), KPH COMPOUND, BULANAO, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2018₱77.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNOR ROY PADILLA SR. MEMORIAL STADIUM), CAMARINES NORTE, JOSE PANGANIB

Region V, Region V

2024₱57.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TATAG NG INPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF QUIRINO PROVINCIAL MOBILE FORCE COMPANY

Region II, Region II

2021₱54.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE(3) UNIT TWO(2) STOREY TEN(10) CLASSROOM AT P. ROMAN NATIONAL HIGH SCHOOL, PILAR, BATAAN

Bataan 2nd DEO, Region III

2016₱44.0M
Reported complete (DPWH)
No sat.

CLUSTER: CONSTRUCTION OF ONE (1) STOREY ONE (1) CLASSROOM AND TWO (2) STOREY FOUR (4) CLASSROOM , SIX (6) CLASSROOM AND TEN (10) CLASSROOM SCHOOL BUILDINGS AT DEL GALLEGO AND RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2016₱40.0M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING, DMMMSU MLUC, PHASE II, BARANGAY CATBANGEN, CITY OF SAN FERNANDO, LA UNION (RE-ADVERTISEMENT)

La Union 1st DEO, Region I

2024₱39.6M
Reported complete (DPWH)
View all 107 projects →

4. Implementation

Contract Amount

₱51,340,000.00

Progress

Reported complete (DPWH)

Start Date

December 16, 2019

Target End

December 24, 2020

5. Audit