Flood Control and Drainage25G00041

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AKLAN RIVER, PACKAGE 4, KALIBO, AKLAN

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AKLAN RIVER, PACKAGE 4, KALIBO, AKLAN is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱124,573,407.65. Status: Past target date (DPWH On-Going). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱124,573,407.65

Progress

Past target date (DPWH On-Going)

Start Date

February 14, 2025

Target End

January 27, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.