CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DODIONGAN FALLS, BRGY. BONBONON, ILIGAN CITY, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱39,690,000.00. Status: Reported complete (DPWH). Contractor on record: A C RIVERO DEVELOPMENT CORP. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Pendolunan, Munai, Lanao del Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Lanao del Norte 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

736 projects · ₱22.2B total · 19 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BRIDGE, BARANGAY TALABAN, HIMAMAYLAN CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2021₱183.3M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD WITH SEAWALL, BARANGAY TABA-TABA TO BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE, B

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS DAANG MAHARLIKA (LZ),K0356+076-K0357+377.00; K0357+406-K0357+894.00; K0357+920.00-K0358+819.00, CAMARINES NORTE 2ND LEGISLATIVE DISTRICT

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS: JUBAN-MAGALLANES ROAD, JUBAN AND MAGALLANES, SORSOGON PROVINCE

Region V, Region V

2018₱139.7M
Reported complete (DPWH)
No sat.

CONST. OF CONCRETE ROAD - BRGY. SAN ANTONIO - CONDEZ - SAN LUIS - SAN VICENTE - FLORES ROAD LEADING

Region VI, Region VI

2017₱134.8M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CLUSTER V-I-REHABILITATION/IMPROVEMENT OF REVETMENT ALONG BARANGAY BAGACAY-PACO SECTION, BOTH SIDE

Region V, Region V

2021₱130.4M
Past target date (DPWH On-Going)
View all 736 projects →

4. Implementation

Contract Amount

₱39,690,000.00

Progress

Reported complete (DPWH)

Start Date

February 14, 2020

Target End

September 16, 2020

5. Audit