Buildings and Facilities21PE0082

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY BATAN, KABAYAN, BENGUET

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY BATAN, KABAYAN, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱5,938,974.97. Status: Reported complete (DPWH). Contractor on record: ALMOND ENGINEERING. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure within Agno River Basin: along Agno River Main (Pacso), Sta. 209 + 980 - Sta. 210 + 610, Kabayan, Benguet
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Benguet 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

28 projects · ₱302.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER LAMAGAN TO GUEDAY SECTION, STA. 8+366 - STA. 8+966 (BS), BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2025₱48.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), LA TRINIDAD, BENGUET (PHASE 1)

Benguet 1st DEO, Cordillera Administrative Region

2023₱29.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD-BAGUIO-BONTOC ROAD JCT. TO BATAN-ADAOAY, KABAYAN, KABAYAN ROAD IN SUPPORT OF VEGETABLE, PROCESSED TEA AND COFFEE INDUSTRY, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2021₱23.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJORRIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD MITIGATIONSTRUCTURE ALONG AGNO RIVER BASIN, PACSO SECTION, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2020₱19.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD-BAGUIO-BONTOC ROAD JCT. TO BATAN-ADAOAY, KABAYAN ROAD IN SUPPORT OF VEGETABLE, PROCESSED TEA AND COFFEE INDUSTRY, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2022₱17.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG CONG. ANDRES ACOP COSALAN RD, K0312+700-K0312+730, K0313+340-K0313+370, K0314+200-K0314+210, K0316+987-K0317+000, K0319+140-K0319+200, K0319+266-K0319+300, K0319+1252-K0319+1265, K0319+1850-K0319+1855,

Benguet 1st DEO, Cordillera Administrative Region

2022₱15.3M
Reported complete (DPWH)
View all 28 projects →

4. Implementation

Contract Amount

₱5,938,974.97

Progress

Reported complete (DPWH)

Start Date

July 19, 2021

Target End

December 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.