Buildings and Facilities18BE0037

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) BRGY. RAGAN NORTE, DELFIN ALBANO, ISABELA

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) BRGY. RAGAN NORTE, DELFIN ALBANO, ISABELA is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱1,410,875.35. Status: Reported complete (DPWH). Contractor on record: 969 CONST. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,410,875.35

Progress

Reported complete (DPWH)

Start Date

February 15, 2018

Target End

June 14, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.