Construction of Flood Mitigation Structure24EF0013

Construction of Salogon River Flood Control Structure, Brooke's Point, Palawan

Construction of Salogon River Flood Control Structure, Brooke's Point, Palawan is a DPWH-tracked public work in BROOKE'S POINT (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱48,995,638.54. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to sumbong.

BROOKE'S POINT (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Salogon River Flood Control Structure, Brooke's Point, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008380

₱1,845,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0018310

₱857,724.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0002546

₱383,639.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008394

₱170,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,995,638.54

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

August 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.