Construction of Flood Mitigation Structure23DE0019

Construction of Flood Control Structure at Barangay San Isidro (Section 2), Batangas City

Construction of Flood Control Structure at Barangay San Isidro (Section 2), Batangas City is a DPWH-tracked public work in BATANGAS CITY (CAPITAL) (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱39,200,000.00. Status: Reported complete (DPWH). Contractor on record: VICMAR CONST INC. Figures trace to sumbong.

BATANGAS CITY (CAPITAL) (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay San Isidro (Section 2), Batangas City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,200,000.00

Progress

Reported complete (DPWH)

Start Date

February 8, 2023

Target End

August 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.