Roads24FN0033

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - NABUA-BALATAN RD - K0487 + 859 - K0487 + 945

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - NABUA-BALATAN RD - K0487 + 859 - K0487 + 945 is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: MPIRE NINE CONST OPC. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Burabod Creek, Tigaon, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Camarines Sur 5th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

25 projects · ₱335.4M total · 0 flags

Other projects by this contractor

No sat.

OO1: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MILAOR-PILI BYPASS ROAD (PACKAGE 6), CAMARINES SUR

Camarines Sur 2nd DEO, Region V

2025₱29.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PAMPLONA-SAN FERNANDO BYPASS ROAD (PACKAGE 7), CAMARINES SUR

Camarines Sur 2nd DEO, Region V

2025₱29.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0406+912-K0407+000, K0407+216-K0407+500, LIBMANAN, CAMARINES SUR (2ND LEGSLATIVE DISTRICT)

Region V, Region V

2025₱21.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0478+537.11-K0478+861.00, BATO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT)

Region V, Region V

2024₱18.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0429+183-K0429+250, K0429+264-K0429+385, K0429+404-K0429+440, K0429+450-K0429+495, K0429+516-K042

Region V, Region V

2024₱17.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0463+000-K0463+417, BAAO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT)

Region V, Region V

2024₱16.6M
Past target date (DPWH On-Going)
View all 25 projects →

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

April 24, 2024

Target End

November 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.