Buildings and Facilities18KC0013

CLUSTER 1 CONST. (COMPLETION) OF COVERED COURT, MANOLO FORTICH, BUKIDNON (A) CONST. (COMPLETION) OF COVERED COURT, ALAE CES, BRGY. ALAE (B) CONST. (COMPLETION) OF COVERED COURT, BRGY. LINGION (C) CONST. (COMPLETION) OF COVERED COURT, STO. NINO

CLUSTER 1 CONST. (COMPLETION) OF COVERED COURT, MANOLO FORTICH, BUKIDNON (A) CONST. (COMPLETION) OF COVERED COURT, ALAE CES, BRGY. ALAE (B) CONST. (COMPLETION) OF COVERED COURT, BRGY. LINGION (C) CONST. (COMPLETION) OF COVERED COURT, STO. NINO is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱2,857,140.00. Status: Reported complete (DPWH). Contractor on record: D2J BUILDERS VENTURE. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Sayre Highway with slope protection, Alae-Kisolon Section, Maluko, Manolo Fortich, Bukidnon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-18-0005873

₱1,778,742.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱2,857,140.00

Progress

Reported complete (DPWH)

Start Date

March 15, 2018

Target End

June 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.