Roads17BE0026

CONCRETING OF LULLUTAN-CABANNUNGAN FIRST ROAD LULLUTAN-CABANNUNGAN FIRST, CITY OF ILAGAN, ISABELA

CONCRETING OF LULLUTAN-CABANNUNGAN FIRST ROAD LULLUTAN-CABANNUNGAN FIRST, CITY OF ILAGAN, ISABELA is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱15,985,133.90. Status: Reported complete (DPWH). Contractor on record: DRAGON TWELVE BUILDERS & CONST SUPPLY 39808. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 39808

21 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY

Region II, Region II

2025₱253.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, IL

Region II, Region II

2024₱192.8M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD: BRIDGE - WIDENING OF PERMANENT BRIDGES - ARCON BRIDGE (B01130LZ) ALONG DAANG MAHARLIKA (LZ)

Region II, Region II

2022₱155.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, P

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, P

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ILAGAN CITY BYPASS ROAD, ISABELA

Region II, Region II

2025₱115.2M
Past target date (DPWH On-Going)
View all 21 projects →

4. Implementation

Contract Amount

₱15,985,133.90

Progress

Reported complete (DPWH)

Start Date

March 27, 2017

Target End

June 19, 2017

5. Audit