Roads22PL0037

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS-BULANAO-PARACELIS ROAD-K0504+236-K0504+540, K0513+230-K0513+321

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS-BULANAO-PARACELIS ROAD-K0504+236-K0504+540, K0513+230-K0513+321 is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱5,471,991.15. Status: Reported complete (DPWH). Contractor on record: BMJ BUILDERS. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Central School/ Sunrise/ Pinuk-Balan, Purok 7/ Hilltop (Cliff) Flood Control, Barangay Dagupan/ Bulanao, Tabuk City, Kalinga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Lower Kalinga DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

49 projects · ₱553.3M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CHICO RIVER AT DAMSITE

Lower Kalinga DEO, Cordillera Administrative Region

2025₱49.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES, CONSTRUCTION OF DPWH MOUNTAIN PROVINCE 2ND DEO SUPPORT FACILITIES (COMPLETION), SALIOK, NATONIN, MOUNTAIN PROVINCE

Mountain Province 2nd DEO, Cordillera Administrative Region

2023₱29.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF NGIPEN, BANTAY FLOOD CONTROL ALONG CHICO RIVER, BANTAY, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2019₱28.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CAGALUAN-CALAN

Lower Kalinga DEO, Cordillera Administrative Region

2024₱24.8M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF DPWH UPPER KALINGA DISTRICT ENGINEERING OFFICE BUILDING, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2021₱24.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF LEVEL III WATER SUPPLY PROJECT, TANUDAN, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2021₱24.4M
Reported complete (DPWH)
View all 49 projects →

4. Implementation

Contract Amount

₱5,471,991.15

Progress

Reported complete (DPWH)

Start Date

April 8, 2022

Target End

July 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.