Flood Control and Drainage21OC0050

REHABILITATION/UPGRADING AND DRAINAGE IMPROVEMENT ALONG CAMIA ST. AND ITS VICINITY, BARANGAY GUADALUPE VIEJO,MAKATI CITY, METRO MANILA

REHABILITATION/UPGRADING AND DRAINAGE IMPROVEMENT ALONG CAMIA ST. AND ITS VICINITY, BARANGAY GUADALUPE VIEJO,MAKATI CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱13,512,240.00. Status: Reported complete (DPWH). Contractor on record: BAO-IDANG CONST 23883. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Flood Control River Wall along Polo River, Barangay Tagalag, Valenzuela City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Metro Manila 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱13,512,240.00

Progress

Reported complete (DPWH)

Start Date

April 12, 2021

Target End

January 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.