Buildings and Facilities16DG0015

CONST. OF THREE (3) STOREY SIX (6) CL SB AT PULO NI SARA NHS, MARAGONDON, CAVITE

CONST. OF THREE (3) STOREY SIX (6) CL SB AT PULO NI SARA NHS, MARAGONDON, CAVITE is a DPWH-tracked public work in Cavite 2nd DEO, Region IV-A. Reported contract value: ₱10,240,588.46. Status: Reported complete (DPWH). Contractor on record: BAQPRINCE CONST AND TRADING CORP 28337. Figures trace to dpwh.

Cavite 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 28337

182 projects · ₱6.2B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION (COMPLETION) OF ROSARIO GYMNASIUM, ROSARIO, CAVITE

Cavite 1st DEO, Region IV-A

2024₱147.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT ALONG CAÑAS RIVER, GENERAL TRIAS, CAVITE, PHASE 3

Region IV-A, Region IV-A

2023₱99.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSMALABON GRANDE- SAN JUAN - MULAWIN DIVERSION ROAD, LAVANYA SECTION, BRGY. SAN JUAN II, GEN. TRIAS CITY, CAV

Cavite 1st DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSMALABON GRANDE- SAN JUAN - MULAWIN DIVERSION ROAD, MULAWIN SECTION, SEGMENT 3, TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2022₱96.5M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONST. OF REVETMENT ALONG IMUS RIVER,BRGY.BINAKAYAN, PHASE II

Cavite 1st DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS P BURGOS-POTATANIN JCT - K0153 + (-808) - K0154 + 080, K0154 + 859 - K0155 +000, K0162 + 300 - K0163 + 000, K0177 + 578 - K0178 + 924PADRE BURGOS & AGDANGAN, QUEZON

Quezon 3rd DEO, Region IV-A

2021₱96.5M
Reported complete (DPWH)
View all 182 projects →

4. Implementation

Contract Amount

₱10,240,588.46

Progress

Reported complete (DPWH)

Start Date

May 19, 2016

Target End

October 15, 2016

5. Audit